In September 2003, major construction work began at the IOTA site. Service connections are renewed and an extension building is added. Despite these daytime activities, obstructions for nighttime observations are currently (amazingly enough) not expected.
Check back regularly for an updated progress report and new site pictures of the current month.
Progress report below
|
September |
|
|
October |
|
|
November |
|
|
December |
|
|
January 2004 |
|
|
February 2004 |
|
9/10
UPS disconnected
Building removed
UPS reconnected in building
Blue stake search for trench
Sidewalk demolished
Dig to find trench - only waterline found 3' down
Trench to check power lines
Find 3 conductor power line rather than 4
Find exit of conduits - Telephone not in conduit
Preliminary footing dig
Exit slab removed
Dry well for draining 1 AC unit
10/1
Foundation to go below frost line 3'4" down
Bedrock not found to that depth in most places
Ground rod removed from foundation area
10/6
continue digging foundations
refill dry well temporarily to enable digging foundation
10/7-8
upgrade fire alarm system at IOTA
10/13
Compacted dirt test -passed
Dry well all set with steel plate over top - car safe
12" diameter Perforated pipe 4-5' long on end
AB fill added and compacted to center area
front footing dug
ladder removed
Steel subcontractor checking dimensions
10/16
ground rod put back into ground
lines layed to show location of foundation edges
rebar being installed for first foundation pour
pour in bottom of trench, no forms, 1-2' deep
10/17
Plumbing contractor came in to verify route
for sink pump to an outside barrel. The
dry well has been compacted away and the
sink is not draining well. Work will
probably happen on it next week.
10/23
concrete pour #1 at IOTA
(10 yards to anchor building could have used 1 more)
one truck for IOTA and one for CB.
No revised schedule yet.
10/29
Forms for slab foundation installed
10/30
Plumber looking at sink drain pump and storage tank
rebar for new building started
11/5
concrete floor poured - 3+ trucks worth, 30cu yds
11/10
Steel work erected
11/12
new power cables installed
11/14
new power cables connected
11/20
steel framework skeleton completed, sidewalk framed
11/21
ground ring installed
11/26
sidewalks poured
Steel work delayed by administrative/insurance issues
12/2
river rock distributed around parking area
12/3
met with roofing contractor on membrane roof- Duro-Last
plumber working on pipes to drain sink
contractor drove off road
12/4
meeting
Steel workers put on metal roof
Stairs Welded in place
12/5
sink completed
electrical layout in expansion started
12/6
Masonry work at commons
12/9
Electrical conduit to be installed
Partition wall to be erected
Waiting for steel wall panels.
12/10
panels arrive at basecamp
12/11
meeting
new roof approved, 2 weeks to construct
12/12
electricians roughing out work
12/18
meeting
roof work next week
12/23
Pour concrete for Commons deck
Roof at iota
red iron framing of windows & AC
12/24
Weld door frames in place
finish roof
12/29
cut wall panels to size - clips don't work
12/30
attach wall panels
1/9
Install electrical conduits, plates
1/16
install East window, lightning protection
1/20
install doors and lights
1/27
install 3 Western windows
2/4
Seal wall openings, flash window interiors
2/5
move exterior doors
Corners being sealed with flashing
2/6
Install storage room AC unit
Install Main room Interior AC unit
2/10
walls painted
2/13
sink installed
2/16
Doors painted with second coat
2/18
carpet installed
door thresholds installed
2/19
UPS moved, permanent wiring made
2/20
New Transformer installed
2/23
AC Condenser unit mounted
most door handles installed
2/28
cut opening between old/new buildings
install blackout shades
Future ***
3/2
fix roof leaks
3/4
final inspection
Commons building
basement area excavated
deck demolished
power line ripped out
Water line hit
Water line repaierd
power line repaired
floor leveled and re filled
10/2 Walt hospitalized
10/4 Rebar in place
10/7 pour concrete foundation & floor
10/14 Block delivered - working on wall forms.
10/23 Retaining wall poured ~ 9 yards
10/24 Framing walls for rooms, demolishing deck
10/28 Building block wall
11/11 New support beams added, deck demo continues
11/26 lift area apron poured
Block wall finished
12/23 Deck concrete poured
1/9 Install garage door
1/16 Paint walls
1/27 Fireproofing
1/29 Ceiling grid installed
1/30 Ceiling panels completed
Electrical/Fire alarms
10/3 Bowl dorm connections added
10/5 Common building redone
10/8 IOTA done
10/10 work started at MMT
11/12 work started at APT